Licences and permits

Obtain a mineral exploration permit

Under the 2019 mining code, exploring for minerals requires an exploration permit issued by order of the minister in charge of mines. It is valid for three years, renewable twice, and covers at most 1,500 km² (5,000 km² for diamonds). Only a company incorporated under Gabonese law with the required technical and financial capacity may apply.

Steps
5
Total indicative delay
Not published
Total indicative cost
Proportional or variable fees
Last validation
21 September 2026
Version 1
Freshness
Up to date

Steps

  1. Incorporate a company under Gabonese law

    What to do

    Apart from individual artisanal mining, only a legal entity incorporated under Gabonese law can hold a mining title. A foreign company with a branch in Gabon can only obtain a reconnaissance authorisation.

    Channel
    Online
    Delay
    Not published
  2. Prepare the application file

    What to do

    Gather the identification and capacity documents required by article 15 of the code: articles and registration data, NIF, CNSS number, annual reports, staff references, evidence of financing and the work and expenditure programme.

    Channel
    At the counter
    Delay
    Not published
  3. File the application with the minister in charge of mines

    What to do

    The application is addressed to the minister in charge of mines and recorded by the mining cadastre service, which handles follow-up and issue. If several applications cover the same area, a competitive review compares technical offers, experience, benefits to the State and local content.

    Channel
    At the counter
    Delay
    Not published
    Fees
    • Award fees and charges set by regulation
  4. Sign the mining agreement

    What to do

    The work and expenditure programme is set out in a mining agreement negotiated under the minister's authority and signed with the State. It sets the project's technical, tax, customs and environmental terms.

    Channel
    At the counter
    Delay
    Not published
  5. Receive the award order

    What to do

    The permit is issued by ministerial order for three years, renewable twice for the same period. Titles subject to the surface rental fee are sent to the Official Journal within 30 days for publication. An operator may not hold more than four exploration permits (two for diamonds).

    Channel
    At the counter
    Delay
    Not published
    Fees
    • Surface rental fee

Process diagram (BPMN)

BPMN diagram

Documents to prepare

Tick each document as you go. Official templates can be downloaded when they exist.

  • Step 2

    Documents required by article 15 of the mining code: identity, address, articles and registration data of the company and of its technical shareholders, NIF, CNSS number, annual reports for the last two years, qualifications and references...

  • Step 2 Issued by Directorate General of Taxes (DGI)

    Certificate issued by the Directorate General of Taxes stating the taxpayer's identification, activity, address and tax identification number (NIF).

  • Steps 2, 4

    Planned exploration work programme, with objectives by category of work and the related spending commitments. It is included in the mining agreement.

Fees

Fees by step
Step Fee Amount Basis Status
3 Award fees and charges set by regulation Not published Variable
5 Surface rental fee Not published Variable

Legal basis

Ask a question about this procedure

The assistant answers from the procedures and texts published on the portal, with sources.

Sources

2 sources cited
Gabon Eco AI